The final footings have been poured for the southeast classrooms. The 2 windows will have a wall in between them separating the 2 classrooms.
The concrete floor in the northeast classrooms was poured on 10/19/09. We finally have an area that is free from mud!
This area will be the future restrooms on the east end of the commons area. Work finished on the outside walls on 10/19/09. Work as slowed as the block masons have fought rain and mud.
Plumbers are roughing in drains in the kitchen area. They have fought extremely wet weather as can be seen by the lumpy terrain.